Our primary school construction in Madagascar is continuing to progress at pace. This week the roof is going on to the new building, which means that the team will be able to begin efforts on the internal fixtures and fittings.
Drilling the well will commence at the end of this week, which is a change in timing but the plan for the drilling itself remains the same. The well is critical to the local community and we are hopeful that it will progress smoothly with our chosen partner. The children are also joining the efforts and helping by planting a beautiful garden outside.
The project is on course to complete at the end of October.